“Our goal is to celebrate and strengthen the Mira Mesa community.” – Mira Mesa Community Champions
Mira Mesa 4th of July Tradition Returns!
Let us keep this tradition alive!
Be part of Mira Mesa’s American Mosaic — Many Cultures, One Community, One Freedom.
THE LATEST FOR MMCC
APRIL 2026 CONSTRUCTION PROGRESS REPORT MIRA MESA COMMUNITY PARK PHASE II IMPROVEMENTS.
Phase II is ongoing, click to see the progress.
Construction Progress Report of March 20 to April 20:
We are approaching the end of the second rainy season (October–April). The total number of non-compensable delay days to date remains 24 since project commencement.
Security cameras have been installed throughout the park by the contractor to help protect the nearly completed facilities. The cameras are programmed to notify the police if unauthorized activity is detected after hours (weekdays from 5:00 p.m. to 5:00 a.m., and all day on weekends). The contractor has also hired a security guard.
The guard is present on site during non-business hours, Monday through Friday, and throughout the weekend to help secure the site.
Ongoing Work:
• Ongoing installation of underground irrigation improvements.
• Ongoing planting of trees and shrubs.
• Ongoing soil amendment of areas to receive new sod.
• Ongoing concrete placement for public artwork benches.
• Ongoing installation of overhead pool plumbing within the equipment building.
• Ongoing construction of the all-wheels plaza.
• Ongoing installation of sports lighting controls.
• Ongoing installation of 20-foot-tall perimeter fencing for ballfields.
• Ongoing installation of gates for trash enclosure.
• Ongoing grading for ballfields #3 and #4 in preparation for new sod placement.
• Ongoing commissioning of HVAC improvements at recreation center and aquatic complex.
• Ongoing installation of site bleachers
Completed Installations and Repairs:
• Tree and sod planting completed within Area 1; plant establishment period completed.
• Installation of handrails at aquatic complex.
• Installation of public artwork structure.
• Installation of bike racks and bike lockers.
Outside agency coordination:
Continued close coordination with the neighboring Epicentre project, managed by the County of San Diego. Continued close coordination with SDG&E planners.
Continue close coordination with DEH inspectors.
Coordination with AT&T planners has been finalized.



Community talks:
“When will the Mira Mesa 4th of July parade come back?”
“Will the Mira Mesa fireworks actually happen on July 4th?”
“Where is the promised new rec with full size basketball gym?”
“When will the Epicentre and Park & Rec center reopen?“
What can we do as a community?
join the Upcoming Event, Register & share
coming soon for NEXT discussion
What are we fighting for?
the new promised gym with full size basketball court